YOUNG & Co BREWERY PLC
BREWHOUSE AUTOMATION
Cilck Image Above to View Full Article
Background
Young & Co.'s Brewery had been considering automating the brewhouse at
the Ram Brewery in Wandsworth, London, for some time but were uneasy due to
previous bad experiences with process control contractors. Following
discussions with Canongate during the latter part of 1999, David Gray, Chief
Engineer at Young's, decided that, due to their unmatched experience in
automation within the brewing industry, Canongate were the right company to
work with.
Brewhouse Control Project
Canongate Technology Ltd. were awarded the contract to project manage,
design, supply and commission a new control and SCADA system for controlling
the mashing process and cleaning of the two conventional Mash Tuns at the
brewery. Canongate Technology Ltd. also project managed, designed and
commissioned the electrical work on-site. The electrical installation contract
was awarded to Nala Engineers Ltd. and the Motor Control Centre contract
awarded to Industrial Display Systems.
The mechanical design aspect of the project was designed and managed by
Young's personnel, with the installation contract being awarded to Shobwood
Engineering (Burton) Ltd.
Process design
As the brewing and cleaning processes were totally manual, a process control
philosophy document was designed in conjunction with brewery personnel. A
Functional Design Specification (FDS) for the project was then produced based
on this agreed document. The FDS was used for all aspects of the control
strategy. The manual equipment that was automated included routing valves,
pumps, level probes, flowmeters, flow control valves etc.
Control System
The control system installed consists of an Allen Bradley SLC5/05
programmable controller with analogue and digital interface. As part of the
project, three existing SLC503's running other operations within the brewery
were upgraded to SLC5/05's. The SLC controls all the process from mashing in,
wort run off, wort copper fill selection, mash tuns grains out, Cleaning In
Place (CIP) and all liquor flushing.
Communications Network
The existing Allen-Bradley DH485 network was replaced with a Local Area
Network (LAN) using Thin Ethernet IEEE802.3 10Base2 Coax in a bus topology. The
SLC and SCADA nodes are directly connected to the network via Hubs and RJ45
patch cords.
SCADA
The SCADA system is Intellution Fix version 7.0 using Allen Bradley RSLinx
to communicate with the SLC's. The operating platform is Microsoft Windows NT.
The system is designed to give the brewer complete control of the mashing
process from recipe menus. There are 20 standard named qualities available from
which the brewer can select to alter brew details or accept the standard brew.
From the selected recipe, dry goods quantity, a liquor to grist ratio and
total volume of wort to be collected and sparge volume to be used is
calculated. The system also has parameters to calculate liquor plate cover
volume, liquor underlet volume, stand times, delay to sparge and wort run off
profile, including wort flow ramp ups, and copper fill volumes. The facility to
alter parameters whilst a brew is in progress is also available to the brewer.
The system also gives real time trends of the wort run off flowrate and sparge
liquor flowrate profiles.
The Clean in Place (CIP) and liquor flushing of the Mash Tuns and wort mains
is also controlled via SCADA selection. All functions are date and time stamped
when last completed. As part of the overall project, modifications to the wort
heat exchanger were also carried out, this included moving temperature control
from panel mounted instruments to the SLC5/05 and the installation of wort
oxygenation and measurement control system.
In order to ensure smooth on-site commissioning, Young's technical and
operation staff spent three consecutive days at Canongate premises for
simulation. During this time some minor changes were introduced. It was felt
that with operators' input at this stage the system would be introduced
seamlessly. With tight production schedules to meet, it was essential that all
changeovers took place over a planned five day period with no production loss.
Conclusion
Following completion of the project in early April 2000, David Gray
commented "the job progressed well with an excellent simulation.
Canongate's understanding of our functional requirements was excellent as was
the quality of hardware and software delivered. The commissioning was carried
out very smoothly with minimal disruption. Altogether an excellent
conclusion".
The Future
Following this very successful project Canongate have already made a start
at the next stage of process automation at the Ram Brewery. This includes
replacement of an old pneumatic panel with all the control being integrated to
the new plc and various smaller, temperature control and rousing control
projects.
David Gray, being of the belief that the client/supplier relationship is of
utmost importance, has invited Canongate engineering staff to discuss his
thoughts for process automation and control work over the next three to five
years.
|